...and they have a plan.
The report from the engineers is complete and the park service now has a plan.
They're going to cover the monument with scaffolding and set up a tower crane to help remove the 1 ton external marble panels at the pyramidal top and re-attach them with metal brackets because the anchor stones underneath were cracked by the quake. The metal brackets will be hidden from view.
They also need to patch 50 panels, but don't expect to need to replace any of them. The work is going to last into 2014 and the monument will remain closed through then.